Shingles on Apr 1, 2026
Hip-roof boathouse in Fox Hollow
Floor system on March 2, rafters on March 12, shingles on April 1, 2026. A covered slip with an enclosed room at the shore end.
Fox Hollow, Lake Gaston

The build, as it was posted
Dates and quotes come from the Twin Lakes job posts. Customer names are left out.
-
Mar 2, 2026
Floor system
“Floor system installed at the job site in Fox Hollow.”
Floor framing on the piles, with the posts for the roof already standing.
-
Mar 12, 2026
Rafters
“Rafter installation at the job site in Fox Hollow.”
The crew sets the hip rafters from the dock.
-
Mar 19, 2026
Roof framing
The rafters from underneath, where they land on the band beam.
Posted without a caption.
-
Mar 19, 2026
Roof decking
Roof sheathing on, with a crew member working on the ridge.
Posted without a caption.
-
Apr 1, 2026
Roof shingles
“Roof shingle installation at the job site.”
Dark shingles on the hip roof, the room at the shore end sided.
Tell Burwell what you want on your shoreline.
Slip size, roof height, a room, a sundeck, a lift. Call, or send the details and we will get back to you.