Sundeck boathouse in Joyceville
A two-level build on the Virginia side: a sundeck with an outside stair over the slip, and an enclosed room under a hip roof. Posted stage by stage from the first pile in June to trim out in August 2026.
Joyceville, VA

The build, as it was posted
Dates and quotes come from the Twin Lakes job posts. Customer names are left out.
-
Jun 9, 2026 (frame from the job video)
Piles driven
“Pole driving at the job site.”
The driving rig works from a barge while the crew guides each pole into place.
-
Jun 12, 2026
Floor system
“Floor system installation complete. Ready for decking.”
Beams and joists tie the piles together and carry the dock level.
-
Jun 21, 2026
Decking
“Decking installation at the job site.”
The walking surface goes down on the floor system.
-
Jun 24, 2026
Ready for upper band and sundeck
“Ready for upper band and sun deck.”
Posts stand at full height, waiting for the band that carries the sundeck.
-
Aug 4, 2026
Trim out
“Trim out in process.”
Siding, stair and trim going on: the sundeck stair runs up the side, the room sits under the hip roof.